An elevated deck (also called a raised deck) offers a great outdoor extension of your indoor living space. While it’s not a job for beginners, adding a deck is a good DIY project with the right planning, skills, and equipment. We’ll walk you through the process from start to finish so you can build your own elevated deck—or so you’ll know what the job involves if you decide to hire a pro!

Part 1
Part 1 of 5:

Putting Your Plan Together

PDF download Download Article
  1. The size and weight-bearing capacity of elevated decks are nearly always controlled by local building codes, so be sure to contact your locality’s code office before beginning your project. You’ll probably need to obtain a building permit as well in order to build an elevated deck (this may not be the case if you’re building an on-the-ground deck).
    • Don’t skip this step! Otherwise, you may discover the hard way that your homeowner’s insurance doesn’t cover injuries that occur on a deck that isn’t permitted and built according to code.
  2. Do this even if you think there’s no way there are any buried gas, water, or electrical lines in the area where you’re going to build the deck. It’s much better to be safe than sorry!
    Advertisement
  3. If you live in an area that gets cold winters, the frost line is the average depth to which the ground freezes. You need to dig at least 6 in (15 cm) below the frost line—or perhaps 12 in (30 cm) or more according to your local building code—to install your deck piers and support posts. Otherwise, the annual freeze-thaw cycle may cause your deck to buckle and potentially fall.
  4. Instead of just “guess-timating” the layout and materials list for your deck, create a specific plan for it. To simplify the process, work with an architect, or engineer or use an online deck-designer tool to plan out the specifications for your elevated deck.
    • While the deck’s structure is typically made from pressure-treated lumber, you have several options for the decking boards you’ll be walking on. You can use a range of natural woods like cedar or redwood, composite (blended wood and plastic) decking, or PVC decking, to name just a few options.
    • Many big-box home improvement stores and decking material producers offer free online deck design tools.
    • Because this is an elevated deck, you’ll have to include railings in your design. You’ll also need stairs, unless you’re building more of a balcony-style deck that doesn’t have direct access to your yard.
  5. Advertisement
Part 2
Part 2 of 5:

Attaching the Ledger Board

PDF download Download Article
  1. Remove any siding so you can mark the lines on the sheathing underneath. Use a level and string a chalk line across the sheathing to mark a line where the top of the ledger board—the connection point between the deck and your home—will attach. Measure down the width of your ledger board—for example, 9.5 in (24 cm) if you’re using a 2 x 10 ledger board—and mark another level chalk line.[1]
    • Remember to factor in the thickness of your decking boards, which will rest on top of the ledger board, when determining the height of your deck in relation to the exterior door you’ll use to access the deck. To reduce the chance of water infiltration (and to keep leaves from blowing in), it’s best to have the tops of the deck boards about 3 in (7.6 cm) below the door threshold.
    • If you’re building the deck off the first level of your home, locate the bottom of the ledger board at least 1.5 in (3.8 cm) above the top of the concrete, stone, or brick foundation. This prevents water from leeching up from the foundation into the ledger board.
  2. If your deck is going to be 10 ft (3.0 m) wide, for example, cut the ledger board to that length. Assuming that you’re building a square or rectangular deck—which you probably should be as a DIYer!—cut the opposing board that will be on the other side of the deck to the same length as the ledger board.[2]
    • In most cases, the opposing board will be a mirror image of the ledger board—the same size, dimensions, and type of wood.
  3. Start at the left side of the ledger board, marking on it the location for the left-side rim joist. Do the same for the right-side rim joist. (Keep in mind when marking these locations that the rim joists are typically 2 standard joists sandwiched together.) Then, mark off on the ledger board the center lines for the deck’s supporting joists that will be spaced out between the rim joists.[3]
    • Repeat this joist-marking process on the ledger board’s opposing board as well.
    • Since the joists will support the deck flooring and provide structural stability, proper spacing based on your design and weight-capacity needs is important. In general, deck joists are spaced 2 ft (61 cm) apart.
  4. Set a joist hanger so it’s centered over one of the spacing lines you marked for the joists on the ledger board. Nail the hanger in place with joist hanger nails, which are fairly short and thick. Continue the process across both the ledger board and to its opposing board.[4]
  5. Line up the ledger board with the lines you put on the house, then temporarily tack it in place with nails. Drill holes into the ledger board for the lag screws—space out either 1 or 2 holes between each joist hanger, depending on how many lag screws you plan calls for. Add a dollop of silicone caulk to each drill hole, then use an impact wrench to sink a lag screw—minimum 12 in (1.3 cm) diameter—into each hole.[5]
  6. Advertisement
Part 3
Part 3 of 5:

Setting the Footings and Posts

PDF download Download Article
  1. Lay out the locations for the footings by running string lines between wood stakes pounded into the ground—use a tape measure and level to make sure the layout is correct. Once you’ve marked each footer location, use either a post-hole digger or power auger to dig the footing holes at least 6–12 in (15–30 cm) deeper than the frost line in your area.[6]
    • Generally speaking, deck footings are spaced about 4–6 ft (1.2–1.8 m) apart, and rarely if ever more than 8 ft (2.4 m) apart.
    • Depending on where you live, your local building inspector may need to check the holes for depth before you can continue.
    • Remember to call 811 to have your utility lines marked before you start digging.
  2. Place a tubular concrete pier form—typically made of either plastic or heavy-duty cardboard—into each hole, then trim the tops of each form as needed so they’re all level. Loosely add backfill around all the forms to hold them in place, then fill each form with concrete.[7]
    • Choose a concrete mix that’s intended for use in footings and mix it according to the product instructions.
  3. Center an anchor bolt (also called a J-bolt) over a concrete-filled pier form and sink the hooked end down into the concrete until only the threaded top portion of the bolt is visible. Repeat this with all the other pier locations, then let the concrete dry for at least 24 hours before moving on to the next step.[8]
    • Use anchor bolts that coordinate with the metal post bases you’ve chosen to use to attach the deck posts to the concrete footings.
  4. Slip a post base over one of the exposed anchor bolts, then slide on a washer and nut. Hand-tighten the nut for now—you can tighten it fully once you confirm everything is in the proper position. Attach the other post bases in the same fashion.[9]
    • Post bases are designed to keep the wood posts from coming in direct contact with the concrete footings. Without them, moisture will wick up from the concrete into the wood and may cause it to rot prematurely.
  5. Set one of the posts down into one of the post bases, check for fit and positioning, then move the post and fully tighten the nut on the post base’s anchor bolt. Return the wood post to its position and lock it in place with the structural screws that come with the post base. Attach all the other posts the same way.[10]
    • Regularly check to confirm that the posts are level and square. Temporarily hold them in the proper position with braces made of scrap lumber.
    • Cut off the tops of the posts to the correct height once all of them are in place.
  6. Advertisement
Part 4
Part 4 of 5:

Laying the Floor Structure and Decking

PDF download Download Article
  1. Set the board—which may be a pair of 2 x 10 boards sandwiched together, depending on your design and local building code—on the posts at the far end of the deck. Once you confirm the board is square and level, attach it with lag screws or lag bolts.[11]
  2. Slide the rim joists—which, along with the ledger board and its opposing board, complete the perimeter of your deck—into the joist hangers at the ends of the ledger board and its opposing board. Secure them in place with galvanized nails or decking screws.[12]
    • Continue to regularly check for level and square as you work.
    • If you’re using pressure-treated lumber, brush some end-grain sealer onto the cut ends to help prevent rot.
  3. Before installation, look down the length of each joist and check signs of bowing (called a crown). If you see a crown, install the joist with the crown pointing up so it will flatten out over time. Secure all the joists into place by driving nails or screws through the hangers.[13]
    • Tap the joists into place with a hammer if it’s a snug fit between the joist hangers. However, trim off a bit of the joist instead of bashing at it with the hammer in order to squeeze it into the hangers. The joists need a bit of room for natural expansion and contraction with the weather.
  4. Start at the ledger board and cut the first 2 deck boards exactly to length—either equal to the width between the rim joists or slightly wider to account for any skirting you plan to add later. The other deck boards can be cut to length after installation with a circular saw or jigsaw. Install the first deck board flush against the house, driving 2 deck screws through the board and into each joist.[14] For each subsequent deck board, leave a space equivalent to the width of a 10-penny nail—about 14 in (0.64 cm)—between boards to allow for water drainage.
    • If you’re using composite or PVC decking, you might be instructed to use a special decking jig that allows you to drive screws or nails into the sides of the deck boards instead of straight down from above. This makes the fasteners invisible once the deck is complete.
    • If your deck is wider than your deck boards, cut the boards so they join right over a joist. Stagger these joints with each row of deck boards so they don’t all end up on the same joist.
  5. Advertisement
Part 5
Part 5 of 5:

Adding Skirting, Railings, and Stairs

PDF download Download Article
  1. A skirting board is an optional element that is simply used to conceal the structural wood beneath. If you choose to add one, cut the skirting boards—you might use 2 x 10 boards, for instance—to length and nail or screw them to the rim joists and the beam that runs opposite to the ledger board. Use simple butt joints instead of angled miter joints at the corners to limit noticeable gaps when the wood expands and contracts with the weather.
    • Add the skirting board before installing the railings and stairs. Or just skip this optional element and move on to those components of the deck.
  2. All elevated decks need railings as a safety measure, and your local building code will dictate elements such as height and spacing. Adding a railing varies based on a lot of design and code factors, but here’s a general rundown:[15]
    • Cut notches into the bottoms of the 4 x 4 (or similar) posts so they will partially rest on the decking and partially overhang the deck.
    • Secure the posts through the skirting board and into the rim joists or beam with at least 2 lag screws or carriage bolts per post.
    • Carefully measure the spacing between posts, then cut and assemble the top and bottom rails and balusters as a unit. Attach each section of railing and balusters between the posts with 3 in (7.6 cm) screws.
  3. Not all elevated decks have stairs, but you’ll need them if you want to access your deck from outside! Building deck stairs is a rather complex process that requires strong math and construction skills, so it’s okay to think about hiring a pro just for this element. That said, here’s a quick summary of the process:[16]
    • Use math (perhaps with the help of an online design tool) to design stairs that meet your local building code—for example, deck stairs often need to be at least 36 in (91 cm) wide, at least 10 in (25 cm) in tread depth, and no more than 7.75 in (19.7 cm) in height per step.
    • Cut the left, right, and center stringers (the supports for the stair treads) out of 2 x 12 boards and attach them to the deck structure with corner brackets, L-brackets, and 3 in (7.6 cm) deck screws.
    • Cut the risers (the vertical part of each step) and attach them to the stringers with deck screws.
    • Trim 1.5 x 10 tread boards to length and connect them to the stringers with 3 in (7.6 cm) deck screws.
    • Add posts and railings in the same way as those on the deck, but this time factoring in for the angle of the stairs.
  4. Advertisement

Expert Q&A

Search
Add New Question
  • Question
    Is a floating deck better?
    Sina Kamran
    Sina Kamran
    Hardscape Specialist
    Sina Kamran is a Hardscaping Specialist and the Owner of Design Scapes, Inc. in Santa Monica, California. With over 15 years of experience, he specializes in customized, site-specific hardscaping and landscaping design/build projects. He's a certified National Concrete Masonry Association (NCMA) designer, a certified installer with the Interlocking Concrete Pavement Institute (ICPI), and a Rain Bird Certified Irrigation Professional. Additionally, Design Scapes, Inc. has many 5-star rated reviews.
    Sina Kamran
    Hardscape Specialist
    Expert Answer
    A floating deck is usually 8 inches off the ground, which makes it easier and simpler to build. For this, you can use prefab concrete anchored into the ground, with about 4 to 6 inches of air for proper ventilation.
Ask a Question
200 characters left
Include your email address to get a message when this question is answered.
Submit
Advertisement

Video

Tips

Submit a Tip
All tip submissions are carefully reviewed before being published
Name
Please provide your name and last initial
Thanks for submitting a tip for review!

Things You'll Need

  • Deck posts (4 x 4s or 6 x 6s)
  • Beams (4 x 6s, 4 x 8s or 4 x 10s, or double or triple layers of 2 x 6s, 2 x 8s or 2 x 10s)
  • Joists (2 x 6s, 2 x 8s or 2 x 10s)
  • Stair stringers (2 x 12s)
  • Deck boards (2 x 4s, 2 x 6s or 5/4 x 6s)
  • Stair treads (same material as deck boards)
  • Railing posts (4 x 4s)
  • Rails (2 x 4s or 2 x 6s)
  • Spindles (2 x 2s)
  • Skirting boards (1 x 8s, 1 x 10s or 1 x 12s)
  • Concrete (ready-mixed or bagged)
  • Concrete pier blocks
  • Joist hangers
  • Common and casing nails (galvanized or coated, 8-, 10- and 16-penny sizes)
  • Screws (galvanized or coated, 2 1/2-inch/6.25 centimeter and 3 1/2-inch/8.75 centimeter)
  • Lag screws and washers
  • Carriage bolts, nuts and washers

Expert Interview

Thanks for reading our article! If you’d like to learn more about building an elevated deck, check out our in-depth interview with Sina Kamran.

About This Article

Sina Kamran
Co-authored by:
Hardscape Specialist
This article was co-authored by Sina Kamran and by wikiHow staff writer, Christopher M. Osborne, PhD. Sina Kamran is a Hardscaping Specialist and the Owner of Design Scapes, Inc. in Santa Monica, California. With over 15 years of experience, he specializes in customized, site-specific hardscaping and landscaping design/build projects. He's a certified National Concrete Masonry Association (NCMA) designer, a certified installer with the Interlocking Concrete Pavement Institute (ICPI), and a Rain Bird Certified Irrigation Professional. Additionally, Design Scapes, Inc. has many 5-star rated reviews. This article has been viewed 45,821 times.
12 votes - 100%
Co-authors: 6
Updated: July 2, 2024
Views: 45,821
Categories: Home and Garden
Thanks to all authors for creating a page that has been read 45,821 times.

Did this article help you?